ITAC Assessment: OK0773
ITAC logo
ITAC Assessment: OK0773
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Organic Chemicals
NAICS 325110: Petrochemical Manufacturing
SIC 2869: Industrial Organic Chemicals, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 3,049,200
ft2
Annual Production 150,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $995,757 15,927,086
kWh
Electricity Demand $62,186 10,885
kW-mo/yr
Natural Gas $1,408,330 192,162
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $55,482 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,712

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1212: Operate boilers on high fire setting $14,770 $22,000 - - $14,770
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,800 - $2,800
44,800
kWh
- -
03 2.2135: Repair and eliminate steam leaks $36,076 $2,450 - - $36,076
-
MMBtu
04 2.7134: Use photocell controls $1,554 $1,284 $752
54,522
kWh
$802
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $201 $1,887 $201
4,992
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $81 $425 $81
3,784
kWh
- -
TOTAL RECOMMENDED $55,482 $28,046 $3,834
108,098
kWh
$802
-
kW-mo/yr
$50,846
-
MMBtu
TOTAL IMPLEMENTED $40,712 $6,046 $3,834
108,098
kWh
$802
-
kW-mo/yr
$36,076
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs