Assessment Year | 2007 |
---|---|
Principal Product | Residential Furniture |
NAICS | 337122: Nonupholstered Wood Household Furniture Manufacturing |
SIC | 2511: Wood Household Furniture, Except Upholstered |
Sales Range | $50 M to 100M |
# of Employees | 381 |
Plant Area |
480,000
ft2
|
Annual Production | 150,000
pieces
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $226,514 | 5,054,400 |
kWh
|
$0.045 |
Electricity Demand | $163,500 | 16,399 |
kW-mo/yr
|
$9.97 |
Electricity Fees | $10,329 | - |
|
- |
Natural Gas | $29,794 | 2,607 |
MMBtu
|
$11.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $71,521 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $45,148 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 4.611: Begin a practice of predictive / preventative maintenance | $3,500 | - | - | - | $3,500 | |
02 | 2.8121: Apply for tax-free status for energy purchases | $13,115 | $1,600 | - | - | $13,115 | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,872 | $1,000 |
$4,872
131,072
kWh
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $3,351 | $4,638 | - |
$3,351
-
MMBtu
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,311 | $814 |
$1,311
15,774
kWh
|
- | - | |
06 | 2.7232: Replace existing hvac unit with high efficiency model | $4,226 | $113,794 | - |
$4,226
-
MMBtu
|
- | |
07 | 2.8121: Apply for tax-free status for energy purchases | $32,400 | $320 | - | - | $32,400 | |
08 | 2.7496: Install partitions to reduce size of conditioned space | $660 | $5,303 |
$283
6,317
kWh
|
$377
-
MMBtu
|
- | |
09 | 2.2625: Chill water to the highest temperature possible | $8,086 | - |
$8,086
180,498
kWh
|
- | - | |
TOTAL RECOMMENDED | $71,521 | $127,469 |
$14,552
333,661
kWh
|
$7,954
-
MMBtu
|
$49,015 | ||
TOTAL IMPLEMENTED | $45,148 | $5,772 |
$9,397
196,272
kWh
|
$3,351
-
MMBtu
|
$32,400 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs