ITAC Assessment: OK0735
ITAC logo
ITAC Assessment: OK0735
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product meat products
NAICS 311612: Meat Processed from Carcasses
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $5
M
to 10
M
# of Employees 600
Plant Area 225,000
ft2
Annual Production 245,000,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $675,376 182,448,000
kWh
Electricity Demand $244,579 40,968
kW-mo/yr
Natural Gas $982,740 131,582
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $122,667 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1241: Reduce excessive boiler blowdown $69,788 $55,933 - $69,788
-
MMBtu
02 2.2414: Use waste heat from hot flue gases to preheat $13,821 $9,500 - $13,821
-
MMBtu
03 2.1233: Analyze flue gas for proper air/fuel ratio $29,625 $4,000 - $29,625
-
MMBtu
04 2.6231: Utilize controls to operate equipment only when needed $8,193 $12,830 $8,193
221,420
kWh
-
05 2.2136: Install / repair insulation on steam lines $1,240 $700 - $1,240
-
MMBtu
TOTAL RECOMMENDED $122,667 $82,963 $8,193
221,420
kWh
$114,474
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs