ITAC Assessment: OK0725
ITAC logo
ITAC Assessment: OK0725
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Poultry Products
NAICS 311615: Poultry Processing
SIC 2015: Poultry Slaughtering and Processing
Sales Range $100
M
to 500
M
# of Employees 620
Plant Area 69,091
ft2
Annual Production 400,000,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $357,023 10,610,775
kWh
Electricity Demand $221,790 20,370
kW-mo/yr
Electricity Fees $17,334 -
Natural Gas $205,796 29,337
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $78,490 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $36,035 $14,223 - $36,035 -
02 2.2511: Insulate bare equipment $1,143 $339 - - $1,143
-
MMBtu
03 2.7135: Install occupancy sensors $365 $437 $365
10,483
kWh
- -
04 2.2437: Recover waste heat from equipment $29,580 $24,609 - - $29,580
-
MMBtu
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,367 $27,265 $11,367
326,633
kWh
- -
TOTAL RECOMMENDED $78,490 $66,873 $11,732
337,116
kWh
$36,035 $30,723
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs