Assessment Year | 2005 |
---|---|
Principal Product | Powder Coated Parts |
NAICS | 333999: All Other Miscellaneous General Purpose Machinery Manufacturing |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 28 |
Plant Area |
50,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $53,440 | 688,380 |
kWh
|
$0.078 |
Natural Gas | $126,696 | 16,196 |
MMBtu
|
$7.82 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,498 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,523 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2211: Use optimum temperature | $10,475 | $1,000 | - | - |
$10,475
-
MMBtu
|
- | - | - | |
02 | 2.1133: Adjust burners for efficient operation | $10,780 | $4,636 | - | - |
$10,780
-
MMBtu
|
- | - | - | |
03 | 3.2176: Increase use of automation | $10,975 | $6,000 |
$463
17,456
kWh
|
- | - | - | $10,512 | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $786 | $5,290 |
$256
9,651
kWh
|
$388
-
kW-mo/yr
|
- | $142 | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,282 | $9,940 |
$655
24,700
kWh
|
$931
-
kW-mo/yr
|
- | $(-304.0) | - | - | |
06 | 4.611: Begin a practice of predictive / preventative maintenance | $5,200 | - | - | - | - | - | - | $5,200 | |
TOTAL RECOMMENDED | $39,498 | $26,866 |
$1,374
51,807
kWh
|
$1,319
-
kW-mo/yr
|
$21,255
-
MMBtu
|
$(-162.0) | $10,512 | $5,200 | ||
TOTAL IMPLEMENTED | $28,523 | $20,866 |
$911
34,351
kWh
|
$1,319
-
kW-mo/yr
|
$21,255
-
MMBtu
|
$(-162.0) | - | $5,200 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs