ITAC Assessment: OK0711
ITAC logo
ITAC Assessment: OK0711
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Polyethylene Stretch Film
NAICS 327212: Other Pressed and Blown Glass and Glassware Manufacturing
SIC 3085: Plastics Bottles
Sales Range $50
M
to 100
M
# of Employees 80
Plant Area 113,000
ft2
Annual Production 76,834,000
thousand feet
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $451,778 -
Electricity Demand $45,354 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $252,270 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,068 $25,248 $10,068
267,778
kWh
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $333 $647 $189
10,080
kWh
$144
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,907 $3,150 $1,102
58,815
kWh
$805
-
kW-mo/yr
-
04 2.2625: Chill water to the highest temperature possible $13,929 $125 $8,055
430,041
kWh
$5,874
-
kW-mo/yr
-
05 4.611: Begin a practice of predictive / preventative maintenance $8,800 - - - $8,800
06 2.7135: Install occupancy sensors $846 $811 $846
45,178
kWh
- -
07 2.3191: Use demand controller or load shedder $215,784 $8,400 - $215,784
-
kW-mo/yr
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $603 $4,626 $277
14,764
kWh
$376
-
kW-mo/yr
$(-50.4)
TOTAL RECOMMENDED $252,270 $43,007 $20,537
826,656
kWh
$222,983
-
kW-mo/yr
$8,750
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs