ITAC Assessment: OK0708
ITAC logo
ITAC Assessment: OK0708
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Business forms
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 143
Plant Area 110,000
ft2
Annual Production 312,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $185,553 3,858,984
kWh
Electricity Demand $38,486 8,458
kW-mo/yr
Electricity Fees $207 -
Natural Gas $21,780 2,393
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $78,032 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $69,232

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $4,172 $6,087 $157
3,259
kWh
$55
-
kW-mo/yr
- $3,960 -
02 2.4231: Reduce the pressure of compressed air to the minimum required $4,394 $6,700 $3,521
73,192
kWh
$873
-
kW-mo/yr
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,314 $1,327 $6,322
131,431
kWh
$2,192
-
kW-mo/yr
- $(-200.0) -
04 4.611: Begin a practice of predictive / preventative maintenance $8,800 - - - - $8,800 -
05 2.7241: Install outside air damper / economizer on hvac unit $37,832 $13,050 $37,832
786,530
kWh
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $9,450 $26,280 $7,011
145,766
kWh
$2,439
-
kW-mo/yr
- - -
07 3.5217: Reuse / recycle/ sell paper products $5,070 $700 - - $2,080
-
lb
$(-2,600.0) $5,590
TOTAL RECOMMENDED $78,032 $54,144 $54,843
1,140,178
kWh
$5,559
-
kW-mo/yr
$2,080
-
lb
$9,960 $5,590
TOTAL IMPLEMENTED $69,232 $54,144 $54,843
1,140,178
kWh
$5,559
-
kW-mo/yr
$2,080
-
lb
$1,160 $5,590
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs