| Assessment Year | 2004 |
|---|---|
| Principal Product | Portion Control Meats |
| NAICS | 311611: Animal (except Poultry) Slaughtering |
| SIC | 2011: Meat Packing Plants |
| Sales Range | $10 M to 50M |
| # of Employees | 170 |
| Plant Area |
12,000
ft2
|
| Annual Production | 12,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $141,811 | 1,662,410 |
kWh
|
$0.085 |
| Electricity Demand | $40,865 | 4,654 |
kW-mo/yr
|
$8.78 |
| Electricity Fees | $20,576 | - |
|
- |
| Natural Gas | $13,030 | 1,477 |
MMBtu
|
$8.82 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,345 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $7,853 | $8,000 | - |
$7,853
-
kW-mo/yr
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,548 | $825 |
$537
6,290
kWh
|
$76
-
kW-mo/yr
|
$1,200 | $1,735 | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,490 | $5,298 |
$1,490
17,468
kWh
|
- | - | - | |
| 04 | 2.7135: Install occupancy sensors | $1,980 | $269 |
$1,980
23,213
kWh
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,199 | $287 |
$790
9,266
kWh
|
$18
-
kW-mo/yr
|
- | $391 | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,275 | $8,882 |
$2,482
29,097
kWh
|
$495
-
kW-mo/yr
|
- | $(-702.0) | |
| TOTAL RECOMMENDED | $18,345 | $23,561 |
$7,279
85,334
kWh
|
$8,442
-
kW-mo/yr
|
$1,200 | $1,424 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs