| Assessment Year | 2004 |
|---|---|
| Principal Product | Carbonated Beverages |
| NAICS | 312111: Soft Drink Manufacturing |
| SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
| Sales Range | $100 M to 500M |
| # of Employees | 400 |
| Plant Area |
150,000
ft2
|
| Annual Production | 17,000,000
pieces
|
| Production Hrs. Annual | 5,200
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $266,155 | 10,719,100 |
kWh
|
$0.025 |
| Electricity Demand | $155,233 | 25,827 |
kW-mo/yr
|
$6.01 |
| Electricity Fees | $(-10,980.0) | - |
|
- |
| Natural Gas | $103,243 | 26,380 |
MMBtu
|
$3.91 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $68,843 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $32,832 | $29,700 | - | - |
$32,832
-
MMBtu
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,754 | $11,650 |
$4,754
124,134
kWh
|
- | - | - | |
| 03 | 2.2437: Recover waste heat from equipment | $6,784 | $11,990 | - | - |
$6,784
-
MMBtu
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $2,056 | $656 |
$1,318
53,165
kWh
|
$738
-
kW-mo/yr
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,502 | - |
$2,502
65,334
kWh
|
- | - | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,158 | $5,157 |
$3,041
122,626
kWh
|
$117
-
kW-mo/yr
|
- | - | |
| 07 | 2.7221: Lower temperature during the winter season and vice-versa | $1,565 | $789 | - | - |
$1,565
-
MMBtu
|
- | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,192 | $655 |
$9,926
400,241
kWh
|
$5,554
-
kW-mo/yr
|
- | $(-288.0) | |
| TOTAL RECOMMENDED | $68,843 | $60,597 |
$21,541
765,500
kWh
|
$6,409
-
kW-mo/yr
|
$41,181
-
MMBtu
|
$(-288.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs