ITAC Assessment: OK0676
ITAC logo
ITAC Assessment: OK0676
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product AC & DC Industrial Electric Motors
NAICS 335312: Motor and Generator Manufacturing
SIC 3621: Motors and Generators
Sales Range $50
M
to 100
M
# of Employees 400
Plant Area 150,000
ft2
Annual Production 575,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $224,642 7,570,800
kWh
Electricity Demand $148,739 312,391
kW-mo/yr
Electricity Fees $43,857 -
Natural Gas $107,936 13,281
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,788 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
01 2.7135: Install occupancy sensors $369 $874 $369
18,439
kWh
- - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $2,179 $9,625 $1,577
78,877
kWh
$602
-
kW-mo/yr
- -
03 4.611: Begin a practice of predictive / preventative maintenance $5,300 - - - $5,300 -
04 2.8121: Apply for tax-free status for energy purchases $3,712 $600 - - - $3,712
05 3.4116: Meter recycled water (to reduce sewer charges) $1,578 $242 - - - $1,578
06 2.6218: Turn off equipment when not in use $25,650 $1,690 $5,018
250,918
kWh
$20,632
-
kW-mo/yr
- -
TOTAL RECOMMENDED $38,788 $13,031 $6,964
348,234
kWh
$21,234
-
kW-mo/yr
$5,300 $5,290
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs