| Assessment Year | 2003 |
|---|---|
| Principal Product | Thrust Reversers, Nacelles |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
375,000
ft2
|
| Annual Production | 216
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $299,579 | 12,065,200 |
kWh
|
$0.025 |
| Electricity Demand | $169,901 | 39,975 |
kW-mo/yr
|
$4.25 |
| Electricity Fees | $44,104 | - |
|
- |
| Natural Gas | $65,945 | 11,105 |
MMBtu
|
$5.94 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $65,272 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,851 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,885 | $6,844 | - |
$5,885
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.3132: Recharge batteries on during off-peak demand periods | $28,340 | - | - |
$28,340
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.8121: Apply for tax-free status for energy purchases | $12,626 | $2,000 | - | - | - | $12,626 | - | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $2,333 | $145 |
$1,362
54,912
kWh
|
$971
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,041 | - |
$1,041
41,933
kWh
|
- | - | - | - | |
| 06 | 2.3212: Optimize plant power factor | $1,292 | $8,190 | - | - | - | $1,292 | - | |
| 07 | 3.4116: Meter recycled water (to reduce sewer charges) | $7,225 | $262 | - | - |
$7,225
-
Tgal
|
- | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,952 | $28,902 |
$3,719
149,760
kWh
|
$2,648
-
kW-mo/yr
|
- | - | $(-415.0) | |
| 09 | 2.7135: Install occupancy sensors | $578 | $488 |
$578
23,296
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $65,272 | $46,831 |
$6,700
269,901
kWh
|
$37,844
-
kW-mo/yr
|
$7,225
-
Tgal
|
$13,918 | $(-415.0) | ||
| TOTAL IMPLEMENTED | $19,851 | $2,262 | - | - |
$7,225
-
Tgal
|
$12,626 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs