ITAC Assessment: OK0670
ITAC logo
ITAC Assessment: OK0670
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Raw Poultry Products
NAICS 311615: Poultry Processing
SIC 2015: Poultry Slaughtering and Processing
Sales Range $50
M
to 100
M
# of Employees 1,000
Plant Area 106,000
ft2
Annual Production 72,500,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $666,577 23,342,200
kWh
Electricity Demand $327,927 50,099
kW-mo/yr
Electricity Fees $32,097 -
Natural Gas $1,137,569 204,145
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $167,463 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,412

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $20,939 $27,543 - $20,939
-
kW-mo/yr
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $4,120 - $2,786
118,560
kWh
$1,334
-
kW-mo/yr
- -
03 2.2625: Chill water to the highest temperature possible $12,292 - $9,168
390,135
kWh
$3,124
-
kW-mo/yr
- -
04 2.2437: Recover waste heat from equipment $26,304 $4,211 - - $26,304
-
MMBtu
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $43,797 $113,450 $43,797
1,863,175
kWh
- - -
06 2.7135: Install occupancy sensors $1,771 $1,017 $1,771
75,348
kWh
- - -
07 4.441: Install automatic packing equipment $58,240 $6,500 - - - $58,240
TOTAL RECOMMENDED $167,463 $152,721 $57,522
2,447,218
kWh
$25,397
-
kW-mo/yr
$26,304
-
MMBtu
$58,240
TOTAL IMPLEMENTED $16,412 - $11,954
508,695
kWh
$4,458
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs