Assessment Year | 2002 |
---|---|
Principal Product | Specialty Needles |
NAICS |
n/a
|
SIC | 3841: Surgical and Medical Instruments and Apparatus |
Sales Range | $100 M to 500M |
# of Employees | 150 |
Plant Area |
58,650
ft2
|
Annual Production | 14,000,000
pieces
|
Production Hrs. Annual | 4,780
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $203,671 | 3,112,280 |
kWh
|
$0.065 |
Electricity Demand | $7,004 | - |
|
- |
Electricity Fees | $12,843 | - |
|
- |
Natural Gas | $12,274 | 4,826 |
MMBtu
|
$2.54 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,739 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,541 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $6,131 | - | - | - |
$6,201
-
MMBtu
|
- | $(-70.0) | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,120 | $6,442 |
$1,651
25,257
kWh
|
$174
-
kW-mo/yr
|
- | - | - | $295 | |
03 | 2.7135: Install occupancy sensors | $1,798 | $862 |
$1,626
24,856
kWh
|
$172
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7124: Make a practice of turning off lights when not needed | $485 | - |
$485
7,412
kWh
|
- | - | - | - | - | |
05 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,536 | $500 | - | - | - |
$1,536
-
Tgal
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $623 | $1,067 |
$563
8,604
kWh
|
$60
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $11,046 | $10 | - | - |
$11,046
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $23,739 | $8,881 |
$4,325
66,129
kWh
|
$406
-
kW-mo/yr
|
$17,247
-
MMBtu
|
$1,536
-
Tgal
|
$(-70.0) | $295 | ||
TOTAL IMPLEMENTED | $4,541 | $8,371 |
$3,840
58,717
kWh
|
$406
-
kW-mo/yr
|
- | - | - | $295 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs