Assessment Year | 2000 |
---|---|
Principal Product | metal components/ custom metal components |
NAICS |
n/a
|
SIC | 3324: Steel Investment Foundries |
Sales Range | $1 M to 5M |
# of Employees | 50 |
Plant Area |
30,000
ft2
|
Annual Production | 3,500,000
units
|
Production Hrs. Annual | 5,840
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $65,941 | 1,904,400 |
kWh
|
$0.035 |
Electricity Demand | $46,229 | - |
|
- |
Electricity Fees | $300 | - |
|
- |
Natural Gas | $36,762 | 7,997 |
MMBtu
|
$4.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $61,503 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,003 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Increase in Production Savings |
---|---|---|---|---|---|---|
01 | 4.111: Add equipment/ operators to reduce production bottleneck | $59,500 | $115,187 | - | $59,500 | |
02 | 2.7229: Air condition only space necessary | $291 | $112 |
$291
8,400
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $67 | $66 |
$67
1,926
kWh
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $596 | $300 |
$596
17,236
kWh
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,049 | - |
$1,049
30,328
kWh
|
- | |
TOTAL RECOMMENDED | $61,503 | $115,665 |
$2,003
57,890
kWh
|
$59,500 | ||
TOTAL IMPLEMENTED | $2,003 | $478 |
$2,003
57,890
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs