ITAC Assessment: OK0605
ITAC logo
ITAC Assessment: OK0605
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Float Glass - Architectural and Automotive
NAICS
n/a
SIC 3211: Flat Glass
Sales Range $100
M
to 500
M
# of Employees 850
Plant Area 1,300,000
ft2
Annual Production 475,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $3,127,457 126,302,843
kWh
Electricity Demand $1,030,954 -
Electricity Fees $1,350 -
Natural Gas $6,558,324 2,843,678
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,788,420 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Demand Savings Personnel Changes Savings Primary Product Savings
01 2.1114: Limit and control secondary combustion air in furnace $6,168,500 $723,000 - - $6,168,500
02 2.1116: Improve combustion control capability $606,630 $500,000 $606,630
-
kW-mo/yr
- -
03 2.2424: Use heat in flue gases to preheat products or materials $606,250 $3,000,000 $606,250
-
kW-mo/yr
- -
04 4.426: Modify workload $1,214,000 $850,000 - $1,214,000 -
05 4.441: Install automatic packing equipment $232,800 $280,000 - $232,800 -
06 4.213: Purchase material from supplier in customized packaging $528,240 $500,000 - $528,240 -
07 4.131: Modify process to reduce material use/cost $5,473,600 $4,750,000 - - $5,473,600
08 4.426: Modify workload $958,400 $500,000 - $958,400 -
TOTAL RECOMMENDED $15,788,420 $11,103,000 $1,212,880
-
kW-mo/yr
$2,933,440 $11,642,100
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Demand Savings Personnel Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs