| Assessment Year | 2000 |
|---|---|
| Principal Product | Steel tools |
| NAICS |
n/a
|
| SIC | 3490: |
| Sales Range | $5 M to 10M |
| # of Employees | 50 |
| Plant Area |
50,000
ft2
|
| Annual Production | 5,000,000
pieces
|
| Production Hrs. Annual | 5,070
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $33,660 | 1,136,870 |
kWh
|
$0.030 |
| Electricity Demand | $36,413 | - |
|
- |
| Electricity Fees | $4,314 | - |
|
- |
| Natural Gas | $7,116 | 1,774 |
MMBtu
|
$4.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,803 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,212 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,212 | $19,769 |
$4,052
136,870
kWh
|
$2,907
-
kW-mo/yr
|
- | - | $253 | |
| 02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $794 | $176 |
$462
15,533
kWh
|
$332
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.3212: Optimize plant power factor | $2,790 | $1,500 | - | - | - | $2,790 | - | |
| 04 | 2.7241: Install outside air damper / economizer on hvac unit | $2,995 | $4,000 |
$2,995
101,114
kWh
|
- | - | - | - | |
| 05 | 4.513: Re-arrange equipment layout to reduce labor costs | $19,012 | $2,700 | - | - | $19,012 | - | - | |
| TOTAL RECOMMENDED | $32,803 | $28,145 |
$7,509
253,517
kWh
|
$3,239
-
kW-mo/yr
|
$19,012 | $2,790 | $253 | ||
| TOTAL IMPLEMENTED | $7,212 | $19,769 |
$4,052
136,870
kWh
|
$2,907
-
kW-mo/yr
|
- | - | $253 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs