ITAC Assessment: KU0489
ITAC logo
ITAC Assessment: KU0489
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product plastic injection molded parts
NAICS
n/a
SIC 3079:
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 51,750
ft2
Annual Production 2,300
ton
Production Hrs. Annual 6,000
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $204,515 4,864,009
kWh
Electricity Demand $63,101 11,100
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,840 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,770

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 2.4133: Use most efficient type of electric motors $5,370 $15,320 $4,160
99,355
kWh
$1,210
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,520 $4,600 $1,090
26,084
kWh
$430
-
kW-mo/yr
- - -
03 2.2511: Insulate bare equipment $1,510 $2,370 $1,170
28,136
kWh
$340
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $450 $540 $130
2,931
kWh
$20
-
kW-mo/yr
- $300 -
05 2.7132: Install timers on light switches in little used areas $200 $300 $200
4,689
kWh
- - - -
06 3.1191: Change procedures / equipment / operating conditions $23,230 $12,470 - - $1,570
-
lb
$860 $20,800
07 3.5315: Lease / purchase baler; sell cardboard to recycler $7,560 $5,000 - - $7,560
-
lb
- -
TOTAL RECOMMENDED $39,840 $40,600 $6,750
161,195
kWh
$2,000
-
kW-mo/yr
$9,130
-
lb
$1,160 $20,800
TOTAL IMPLEMENTED $30,770 $33,230 $5,580
133,059
kWh
$1,660
-
kW-mo/yr
$1,570
-
lb
$1,160 $20,800
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs