Assessment Year | 1999 |
---|---|
Principal Product | Feeds |
NAICS |
n/a
|
SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
34,000
ft2
|
Annual Production | 210,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $139,666 | 4,886,284 |
kWh
|
$0.029 |
Electricity Demand | $31,289 | - |
|
- |
Electricity Fees | $(-21,028.0) | - |
|
- |
Natural Gas | $91,252 | 29,193 |
MMBtu
|
$3.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $51,762 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.444: Install system to collect scrap | $20,078 | $2,250 | n/a | - | - | - | $20,078 | - | - |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $16,905 | - | n/a | - |
$16,905
-
kW-mo/yr
|
- | - | - | - |
03 | 2.1332: Convert combustion equipment to burn natural gas | $7,398 | $31,705 | n/a | - | - | - | - | $7,398 | - |
04 | 2.8113: Purchase gas directly from a contract gas supplier | $3,795 | - | n/a | - | - | - | - | - | $3,795 |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,193 | $3,150 | n/a | - | - |
$2,193
-
MMBtu
|
- | - | - |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $891 | $24 | n/a |
$271
10,551
kWh
|
$620
-
kW-mo/yr
|
- | - | - | - |
07 | 2.2511: Insulate bare equipment | $252 | $1,028 | n/a | - |
$252
-
kW-mo/yr
|
- | - | - | - |
08 | 2.2511: Insulate bare equipment | $250 | $525 | n/a | - |
$250
-
kW-mo/yr
|
- | - | - | - |
TOTAL RECOMMENDED | $51,762 | $38,682 |
$271
10,551
kWh
|
$18,027
-
kW-mo/yr
|
$2,193
-
MMBtu
|
$20,078 | $7,398 | $3,795 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs