ITAC Assessment: OK0584
ITAC logo
ITAC Assessment: OK0584
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Transformers
NAICS
n/a
SIC 3612: Power, Distribution, and Specialty Transformers
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 24,000
ft2
Annual Production 1,000
pieces
Production Hrs. Annual 4,080
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,314 635,111
kWh
Electricity Demand $17,196 2,024
kW-mo/yr
Natural Gas $11,539 4,709
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $43,463 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,001

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $662 $1,778 $662
21,981
kWh
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,195 $331 $2,195
39,859
kWh
- - - -
03 3.5313: Increase amount of waste recovered for resale $1,000 - - - - $1,000
-
lb
-
04 2.7144: Install spectral reflectors / delamp $163 $248 $163
5,569
kWh
- - - -
05 2.3132: Recharge batteries on during off-peak demand periods $6,842 - - - $6,842 - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,001 $300 $907
31,360
kWh
$1,094
-
kW-mo/yr
- - -
07 4.425: Eliminate/reduce redundant inspections $30,600 $15,000 - - - - $30,600
TOTAL RECOMMENDED $43,463 $17,657 $3,927
98,769
kWh
$1,094
-
kW-mo/yr
$6,842 $1,000
-
lb
$30,600
TOTAL IMPLEMENTED $3,001 $300 $907
31,360
kWh
$1,094
-
kW-mo/yr
- $1,000
-
lb
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs