ITAC Assessment: OK0582
ITAC logo
ITAC Assessment: OK0582
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Automobile seals
NAICS
n/a
SIC 3052: Rubber and Plastics Hose and Belting
Sales Range $10
M
to 50
M
# of Employees 438
Plant Area 150,000
ft2
Annual Production 11,000,000
lb
Production Hrs. Annual 5,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $693,264 23,337,632
kWh
Electricity Demand $286,519 44,080
kW-mo/yr
Natural Gas $87,827 28,331
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $146,134 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 2.1331: Burn a less expensive grade of fuel $17,137 $21,900 n/a $11,351
374,560
kWh
$10,380
-
kW-mo/yr
$(-4,594.0)
-
MMBtu
- -
02 3.1191: Change procedures / equipment / operating conditions $2,848 $2,000 n/a $2,848
94,959
kWh
- - - -
03 2.7144: Install spectral reflectors / delamp $5,367 $1,070 n/a $3,698
123,388
kWh
$1,669
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $12,573 $3,864 n/a $8,709
290,445
kWh
$3,864
-
kW-mo/yr
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $13,559 $6,500 n/a $9,336
311,841
kWh
$4,223
-
kW-mo/yr
- - -
06 4.424: Improve space comfort conditioning $56,000 $165,000 n/a - - - - $56,000
07 3.5313: Increase amount of waste recovered for resale $38,250 $10,000 n/a - - - $38,250
-
lb
-
08 3.5313: Increase amount of waste recovered for resale $400 - n/a - - - $400
-
lb
-
TOTAL RECOMMENDED $146,134 $210,334 $35,942
1,195,193
kWh
$20,136
-
kW-mo/yr
$(-4,594.0)
-
MMBtu
$38,650
-
lb
$56,000
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs