| Assessment Year | 1999 |
|---|---|
| Principal Product | Pistons |
| NAICS |
n/a
|
| SIC | 3592: Carburetors, Pistons, Piston Rings, and Valves |
| Sales Range | $10 M to 50M |
| # of Employees | 90 |
| Plant Area |
23,000
ft2
|
| Annual Production | 52,000
units
|
| Production Hrs. Annual | 4,992
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $80,289 | 1,769,344 |
kWh
|
$0.045 |
| Electricity Fees | $1,606 | - |
|
- |
| Natural Gas | $699 | 132 |
MMBtu
|
$5.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $41,965 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7241: Install outside air damper / economizer on hvac unit | $11,374 | $1,400 | n/a |
$11,374
287,808
kWh
|
- | - | - |
| 02 | 2.1331: Burn a less expensive grade of fuel | $(-2,220.0) | $2,395 | n/a |
$(-2,220.0)
(-32,825)
kWh
|
- | - | - |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,695 | $340 | n/a |
$4,695
121,336
kWh
|
- | - | - |
| 04 | 2.7135: Install occupancy sensors | $568 | $1,098 | n/a |
$568
14,361
kWh
|
- | - | - |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $218 | $224 | n/a |
$93
2,345
kWh
|
- | - | $125 |
| 06 | 4.445: Install equipment to move product | $24,960 | $31,000 | n/a | - | - | $24,960 | - |
| 07 | 3.5311: Recover and reuse waste material | $2,370 | $2,000 | n/a | - |
$2,370
-
lb
|
- | - |
| TOTAL RECOMMENDED | $41,965 | $38,457 |
$14,510
393,025
kWh
|
$2,370
-
lb
|
$24,960 | $125 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs