Assessment Year | 1998 |
---|---|
Principal Product | Electrical switchgear controls |
NAICS |
n/a
|
SIC | 3613: Switchgear and Switchboard Apparatus |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
40,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $56,201 | 1,139,215 |
kWh
|
$0.049 |
Electricity Fees | $4,560 | - |
|
- |
Natural Gas | $25,001 | 4,365 |
MMBtu
|
$5.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,918 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,738 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3134: Shift from daytime to nighttime operation | $2,306 | $5,000 | - | $2,306 | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $588 | $1,039 |
$298
8,206
kWh
|
- | - | - | $290 | |
03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $629 | $340 |
$629
17,585
kWh
|
- | - | - | - | |
04 | 2.7135: Install occupancy sensors | $640 | $3,078 |
$640
17,878
kWh
|
- | - | - | - | |
05 | 3.6192: Use a less expensive method of waste removal | $1,911 | - | - | - |
$1,911
-
gal
|
- | - | |
06 | 4.424: Improve space comfort conditioning | $15,475 | $1,800 | - | - | - | $15,475 | - | |
07 | 2.8113: Purchase gas directly from a contract gas supplier | $5,369 | - | - | - | - | $5,369 | - | |
TOTAL RECOMMENDED | $26,918 | $11,257 |
$1,567
43,669
kWh
|
$2,306 |
$1,911
-
gal
|
$20,844 | $290 | ||
TOTAL IMPLEMENTED | $23,738 | $7,839 |
$298
8,206
kWh
|
$2,306 | - | $20,844 | $290 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs