ITAC Assessment: OK0561
ITAC logo
ITAC Assessment: OK0561
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Electrical switchgear controls
NAICS
n/a
SIC 3613: Switchgear and Switchboard Apparatus
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 40,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,080
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $56,201 1,139,215
kWh
Electricity Fees $4,560 -
Natural Gas $25,001 4,365
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,918 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,738

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Other Liquid (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.3134: Shift from daytime to nighttime operation $2,306 $5,000 - $2,306 - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $588 $1,039 $298
8,206
kWh
- - - $290
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $629 $340 $629
17,585
kWh
- - - -
04 2.7135: Install occupancy sensors $640 $3,078 $640
17,878
kWh
- - - -
05 3.6192: Use a less expensive method of waste removal $1,911 - - - $1,911
-
gal
- -
06 4.424: Improve space comfort conditioning $15,475 $1,800 - - - $15,475 -
07 2.8113: Purchase gas directly from a contract gas supplier $5,369 - - - - $5,369 -
TOTAL RECOMMENDED $26,918 $11,257 $1,567
43,669
kWh
$2,306 $1,911
-
gal
$20,844 $290
TOTAL IMPLEMENTED $23,738 $7,839 $298
8,206
kWh
$2,306 - $20,844 $290
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Other Liquid (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs