ITAC Assessment: OK0550
ITAC logo
ITAC Assessment: OK0550
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Spring / frame for furniture
NAICS
n/a
SIC 3495: Wire Springs
Sales Range $10
M
to 50
M
# of Employees 225
Plant Area 230,000
ft2
Annual Production 24,000,000
lb
Production Hrs. Annual 4,000
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $85,729 3,468,933
kWh
Electricity Demand $31,289 -
Electricity Fees $(-3,424.0) -
Natural Gas $195,705 36,452
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $170,425 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,124

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.8113: Purchase gas directly from a contract gas supplier $100,207 - - - - - - $100,207
02 2.5194: Redesign process $26,768 $20,000 - - - - $26,768 -
03 2.7243: Improve air circulation with destratification fans / other methods $8,393 $1,945 - $(-4.0)
-
kW-mo/yr
$(-3.0) - $8,400 -
04 2.8121: Apply for tax-free status for energy purchases $4,343 $4,000 - - - - - $4,343
05 3.5316: Contract a wood pallet recycling company $18,120 - - - - $18,120
-
lb
- -
06 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,888 $9,700 - - - $3,888
-
lb
- -
07 2.4231: Reduce the pressure of compressed air to the minimum required $6,071 $8,400 $3,786
153,283
kWh
$2,285
-
kW-mo/yr
- - - -
08 2.2437: Recover waste heat from equipment $1,920 $3,006 $1,920
214,830
kWh
- - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $518 $1,610 $302
12,309
kWh
$216
-
kW-mo/yr
- - - -
10 2.2511: Insulate bare equipment $197 $134 $197
21,981
kWh
- - - - -
TOTAL RECOMMENDED $170,425 $48,795 $6,205
402,403
kWh
$2,497
-
kW-mo/yr
$(-3.0) $22,008
-
lb
$35,168 $104,550
TOTAL IMPLEMENTED $37,124 $14,479 $3,983
175,264
kWh
$2,281
-
kW-mo/yr
$(-3.0) $18,120
-
lb
$8,400 $4,343
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs