Assessment Year | 1997 |
---|---|
Principal Product | Potato salad/ Baked beans |
NAICS |
n/a
|
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
60,000
ft2
|
Annual Production | 18,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $119,454 | 3,155,920 |
kWh
|
$0.038 |
Electricity Demand | $45,069 | 8,514 |
kW-mo/yr
|
$5.29 |
Electricity Fees | $924 | - |
|
- |
Natural Gas | $82,223 | 27,666 |
MMBtu
|
$2.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $74,902 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,718 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2425: Use flue gases to heat process or service water | $17,998 | $48,754 | - | - |
$17,998
-
MMBtu
|
- | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,011 | $3,500 | - | - |
$6,011
-
MMBtu
|
- | - | |
03 | 2.2422: Use waste heat from hot flue gases to generate steam | $3,099 | $4,655 |
$(-135.0)
(-4,689)
kWh
|
- |
$3,234
-
MMBtu
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $962 | $114 |
$744
25,791
kWh
|
$218
-
kW-mo/yr
|
- | - | - | |
05 | 2.2515: Use optimum thickness insulation | $747 | $166 | - | - |
$747
-
MMBtu
|
- | - | |
06 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $6,149 | $12,500 | - | - | - |
$6,149
-
lb
|
- | |
07 | 4.423: Move product using mechanical means | $39,936 | $28,000 | - | - | - | - | $39,936 | |
TOTAL RECOMMENDED | $74,902 | $97,689 |
$609
21,102
kWh
|
$218
-
kW-mo/yr
|
$27,990
-
MMBtu
|
$6,149
-
lb
|
$39,936 | ||
TOTAL IMPLEMENTED | $25,718 | $52,534 |
$744
25,791
kWh
|
$218
-
kW-mo/yr
|
$24,756
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs