| Assessment Year | 1997 |
|---|---|
| Principal Product | aluminium die casts |
| NAICS |
n/a
|
| SIC | 3633: Household Laundry Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
65,000
ft2
|
| Annual Production | 4,500,000
lb
|
| Production Hrs. Annual | 6,552
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $116,271 | 5,182,884 |
kWh
|
$0.022 |
| Electricity Demand | $76,614 | 11,672 |
kW-mo/yr
|
$6.56 |
| Electricity Fees | $13,697 | - |
|
- |
| Natural Gas | $169,087 | 69,971 |
MMBtu
|
$2.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $152,944 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.452: Eliminate shift | $86,855 | $175,000 | - | - |
$(-11,425.0)
-
MMBtu
|
- | - | $98,280 | - | |
| 02 | 2.2442: Preheat combustion air with waste heat | $37,293 | $65,478 |
$(-1,889.0)
(-64,185)
kWh
|
- |
$39,182
-
MMBtu
|
- | - | - | - | |
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $16,057 | $65,478 |
$14,600
495,018
kWh
|
$6,566
-
kW-mo/yr
|
$(-5,109.0)
-
MMBtu
|
- | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,530 | $80,000 |
$5,895
199,590
kWh
|
$2,635
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,329 | $90 |
$1,329
45,135
kWh
|
- | - | - | - | - | - | |
| 06 | 3.5316: Contract a wood pallet recycling company | $1,056 | - | - | - | - | - |
$1,056
-
lb
|
- | - | |
| 07 | 3.6192: Use a less expensive method of waste removal | $816 | - | - | - | - | - |
$816
-
lb
|
- | - | |
| 08 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $741 | - | - | - | - | - |
$741
-
lb
|
- | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $267 | $450 |
$56
1,758
kWh
|
- | - |
$75
-
MMBtu
|
- | $98 | $38 | |
| TOTAL RECOMMENDED | $152,944 | $386,496 |
$19,991
677,316
kWh
|
$9,201
-
kW-mo/yr
|
$22,648
-
MMBtu
|
$75
-
MMBtu
|
$2,613
-
lb
|
$98,378 | $38 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs