Assessment Year | 1997 |
---|---|
Principal Product | Cut up poultry |
NAICS |
n/a
|
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $50 M to 100M |
# of Employees | 1,100 |
Plant Area |
165,000
ft2
|
Annual Production | 265,000,000
lb
|
Production Hrs. Annual | 8,520
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $725,521 | 28,991,794 |
kWh
|
$0.025 |
Electricity Demand | $200,187 | 24,360 |
kW-mo/yr
|
$8.22 |
Natural Gas | $279,016 | 92,263 |
MMBtu
|
$3.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $70,561 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,289 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,774 | $17,415 |
$2,567
102,579
kWh
|
$1,294
-
kW-mo/yr
|
- | - | $(-87.0) | |
02 | 2.1231: Establish burner maintenance schedule for boilers | $7,965 | $5,000 | - | - |
$7,965
-
MMBtu
|
- | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $6,577 | $8,566 | - | - |
$6,577
-
MMBtu
|
- | - | |
04 | 4.513: Re-arrange equipment layout to reduce labor costs | $3,330 | - | - | - | - | - | $3,330 | |
05 | 3.4151: Minimize water usage | $47,695 | $7,520 | - | - | - |
$47,695
-
Tgal
|
- | |
06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,220 | $2,561 |
$2,194
87,632
kWh
|
- |
$(-974.0)
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $70,561 | $41,062 |
$4,761
190,211
kWh
|
$1,294
-
kW-mo/yr
|
$13,568
-
MMBtu
|
$47,695
-
Tgal
|
$3,243 | ||
TOTAL IMPLEMENTED | $16,289 | $24,976 |
$4,761
190,211
kWh
|
$1,294
-
kW-mo/yr
|
$6,991
-
MMBtu
|
- | $3,243 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs