| Assessment Year | 1997 |
|---|---|
| Principal Product | Jeans |
| NAICS |
n/a
|
| SIC | 2325: Men's and Boys' Separate Trousers and Slacks |
| Sales Range | $5 M to 10M |
| # of Employees | 200 |
| Plant Area |
26,000
ft2
|
| Annual Production | 3,500,000
pieces
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $34,342 | 897,714 |
kWh
|
$0.038 |
| Electricity Demand | $18,180 | 2,975 |
kW-mo/yr
|
$6.11 |
| Electricity Fees | $1,968 | - |
|
- |
| Natural Gas | $2,191 | 444 |
MMBtu
|
$4.93 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,333 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,114 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.445: Install equipment to move product | $6,500 | $28,000 | - | - | - | $6,500 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,418 | $22,989 |
$1,762
46,014
kWh
|
$1,656
-
kW-mo/yr
|
- | - | |
| 03 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,589 | - |
$1,589
41,618
kWh
|
- | - | - | |
| 04 | 2.7135: Install occupancy sensors | $199 | $660 |
$199
5,275
kWh
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $69 | $237 |
$56
1,465
kWh
|
$13
-
kW-mo/yr
|
- | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $38 | $50 |
$38
1,758
kWh
|
- | - | - | |
| 07 | 3.5311: Recover and reuse waste material | $600 | - | - | - |
$600
-
lb
|
- | |
| 08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,920 | $21,354 | - | - |
$1,920
-
lb
|
- | |
| TOTAL RECOMMENDED | $14,333 | $73,290 |
$3,644
96,130
kWh
|
$1,669
-
kW-mo/yr
|
$2,520
-
lb
|
$6,500 | ||
| TOTAL IMPLEMENTED | $5,114 | $23,276 |
$3,445
90,855
kWh
|
$1,669
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs