ITAC Assessment: OK0514
ITAC logo
ITAC Assessment: OK0514
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Jeans
NAICS
n/a
SIC 2325: Men's and Boys' Separate Trousers and Slacks
Sales Range $5
M
to 10
M
# of Employees 200
Plant Area 26,000
ft2
Annual Production 3,500,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $34,342 897,714
kWh
Electricity Demand $18,180 2,975
kW-mo/yr
Electricity Fees $1,968 -
Natural Gas $2,191 444
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,333 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,114

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 4.445: Install equipment to move product $6,500 $28,000 - - - $6,500
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,418 $22,989 $1,762
46,014
kWh
$1,656
-
kW-mo/yr
- -
03 2.6212: Turn off equipment during breaks, reduce operating time $1,589 - $1,589
41,618
kWh
- - -
04 2.7135: Install occupancy sensors $199 $660 $199
5,275
kWh
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $69 $237 $56
1,465
kWh
$13
-
kW-mo/yr
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $38 $50 $38
1,758
kWh
- - -
07 3.5311: Recover and reuse waste material $600 - - - $600
-
lb
-
08 3.6193: Install equipment (eg compactor) to reduce disposal costs $1,920 $21,354 - - $1,920
-
lb
-
TOTAL RECOMMENDED $14,333 $73,290 $3,644
96,130
kWh
$1,669
-
kW-mo/yr
$2,520
-
lb
$6,500
TOTAL IMPLEMENTED $5,114 $23,276 $3,445
90,855
kWh
$1,669
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs