ITAC Assessment: OK0510
ITAC logo
ITAC Assessment: OK0510
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Cottonseed Oil, Meal, Lint, Hulls
NAICS
n/a
SIC 2074: Cottonseed Oil Mills
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area
n/a
Annual Production 77,000
pieces
Production Hrs. Annual 8,046
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $372,161 9,950,762
kWh
Electricity Demand $34,594 17,424
kW-mo/yr
Electricity Fees $10,283 -
Natural Gas $602,401 112,066
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,125 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 3.5315: Lease / purchase baler; sell cardboard to recycler $16,000 $7,960 - - $16,000
-
lb
02 2.2136: Install / repair insulation on steam lines $37 $25 - $37
-
MMBtu
-
03 2.4133: Use most efficient type of electric motors $9,445 $588 $9,445
295,135
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $12,303 - $12,303
384,525
kWh
- -
05 2.7134: Use photocell controls $340 $113 $340
10,551
kWh
- -
TOTAL RECOMMENDED $38,125 $8,686 $22,088
690,211
kWh
$37
-
MMBtu
$16,000
-
lb
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs