Assessment Year | 1996 |
---|---|
Principal Product | Mylar and Latex balloons |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
200,000
ft2
|
Annual Production | 28,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $157,946 | 4,143,904 |
kWh
|
$0.038 |
Electricity Demand | $107,571 | 9,468 |
kW-mo/yr
|
$11.36 |
Electricity Fees | $8,762 | - |
|
- |
Natural Gas | $29,990 | 8,163 |
MMBtu
|
$3.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $135,342 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,086 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.8314: Purchase high materials in returnable bulk containers | $91,927 | $31,996 | - | - | - |
$91,927
-
lb
|
|
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $24,329 | $98,000 |
$19,708
368,113
kWh
|
$9,232
-
kW-mo/yr
|
$(-4,611.0)
-
MMBtu
|
- | |
03 | 2.7141: Lower light fixtures in high ceiling areas | $12,077 | $3,040 |
$12,077
182,884
kWh
|
- | - | - | |
04 | 2.2135: Repair and eliminate steam leaks | $5,851 | $3,600 |
$5,851
142,732
kWh
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $689 | $30 |
$689
11,137
kWh
|
- | - | - | |
06 | 2.3132: Recharge batteries on during off-peak demand periods | $469 | $1,000 | - |
$469
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $135,342 | $137,666 |
$38,325
704,866
kWh
|
$9,701
-
kW-mo/yr
|
$(-4,611.0)
-
MMBtu
|
$91,927
-
lb
|
||
TOTAL IMPLEMENTED | $19,086 | $7,670 |
$18,617
336,753
kWh
|
$469
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs