| Assessment Year | 1995 |
|---|---|
| Principal Product | Pier systems |
| NAICS |
n/a
|
| SIC | 3448: Prefabricated Metal Buildings and Components |
| Sales Range | $5 M to 10M |
| # of Employees | 150 |
| Plant Area |
98,285
ft2
|
| Annual Production | 300
pieces
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $33,907 | 599,062 |
kWh
|
$0.057 |
| Natural Gas | $70,986 | 13,359 |
MMBtu
|
$5.31 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $11,314 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,314 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2135: Repair and eliminate steam leaks | $4,457 | $4,457 | - |
$4,232
-
MMBtu
|
$225 | |
| 02 | 2.1321: Replace fossil fuel equipment with electrical equipment | $3,632 | $3,553 | - |
$3,632
-
MMBtu
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,391 | $50 |
$1,391
26,084
kWh
|
- | - | |
| 04 | 2.2136: Install / repair insulation on steam lines | $1,280 | $1,819 | - |
$1,280
-
MMBtu
|
- | |
| 05 | 2.7124: Make a practice of turning off lights when not needed | $554 | - |
$554
10,258
kWh
|
- | - | |
| TOTAL RECOMMENDED | $11,314 | $9,879 |
$1,945
36,342
kWh
|
$9,144
-
MMBtu
|
$225 | ||
| TOTAL IMPLEMENTED | $11,314 | $9,879 |
$1,945
36,342
kWh
|
$9,144
-
MMBtu
|
$225 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs