Assessment Year | 1994 |
---|---|
Principal Product | Asphaltic Concrete |
NAICS |
n/a
|
SIC | 2951: Asphalt Paving Mixtures and Blocks |
Sales Range | $5 M to 10M |
# of Employees | 75 |
Plant Area |
871,200
ft2
|
Annual Production | 260,000
ton
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $90,798 | 1,283,412 |
kWh
|
$0.071 |
Natural Gas | $110,076 | 43,926 |
MMBtu
|
$2.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,359 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings |
---|---|---|---|---|---|---|---|
01 | 2.1113: Reduce combustion air flow to optimum | $23,728 | $4,000 | - |
$23,728
-
MMBtu
|
- | |
02 | 2.2628: Utilize a less expensive cooling method | $3,276 | $11,000 | - | - |
$3,276
-
MMBtu
|
|
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,773 | - |
$1,773
53,048
kWh
|
- | - | |
04 | 2.7134: Use photocell controls | $783 | $180 |
$783
17,585
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $694 | $1,520 |
$694
24,912
kWh
|
- | - | |
06 | 2.2511: Insulate bare equipment | $79 | $125 | - |
$79
-
MMBtu
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $26 | - |
$26
586
kWh
|
- | - | |
TOTAL RECOMMENDED | $30,359 | $16,825 |
$3,276
96,131
kWh
|
$23,807
-
MMBtu
|
$3,276
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs