ITAC Assessment: OK0392
ITAC logo
ITAC Assessment: OK0392
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product BOTTLED BEVERAGES
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 95
Plant Area
n/a
Annual Production 1,500,000
pieces
Production Hrs. Annual 2,340
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,811 611,372
kWh
Natural Gas $12,088 3,848
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,794 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,628

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $15,133 $60,000 $23,850
318,288
kWh
$(-5,117.0)
-
MMBtu
$(-3,600.0)
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,241 - $1,441
40,739
kWh
- $(-200.0)
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,150 - $1,150
14,654
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $104 $210 $129
586
kWh
- $(-25.0)
05 2.2511: Insulate bare equipment $133 $97 $133
9,379
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $33 $29 $33
293
kWh
- -
TOTAL RECOMMENDED $17,794 $60,336 $26,736
383,939
kWh
$(-5,117.0)
-
MMBtu
$(-3,825.0)
TOTAL IMPLEMENTED $2,628 $307 $2,853
65,358
kWh
- $(-225.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs