| Assessment Year | 1992 |
|---|---|
| Principal Product | JELLIES,MUSTARD, & MAYO |
| NAICS |
n/a
|
| SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
n/a
|
| Annual Production | 1,500,000
pieces
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $105,046 | 1,817,995 |
kWh
|
$0.058 |
| Natural Gas | $87,947 | 31,105 |
MMBtu
|
$2.83 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,666 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,081 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,431 | $1,854 |
$5,131
52,462
kWh
|
- | $(-1,700.0) | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,458 | $298 |
$2,458
56,565
kWh
|
- | - | |
| 03 | 2.2136: Install / repair insulation on steam lines | $2,349 | $3,893 | - |
$2,349
-
MMBtu
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,127 | $367 |
$1,258
20,809
kWh
|
- | $(-131.0) | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $185 | $344 |
$238
2,052
kWh
|
- | $(-53.0) | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $495 | - |
$495
7,913
kWh
|
- | - | |
| 07 | 2.2122: Install / repair insulation on condensate lines | $371 | $450 | - |
$371
-
MMBtu
|
- | |
| 08 | 2.2122: Install / repair insulation on condensate lines | $250 | $216 | - |
$250
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $10,666 | $7,422 |
$9,580
139,801
kWh
|
$2,970
-
MMBtu
|
$(-1,884.0) | ||
| TOTAL IMPLEMENTED | $7,081 | $6,757 |
$5,864
62,427
kWh
|
$2,970
-
MMBtu
|
$(-1,753.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs