ITAC Assessment: OK0378
ITAC logo
ITAC Assessment: OK0378
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product PACKAGED JUICE PRODUCTS
NAICS
n/a
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $10
M
to 50
M
# of Employees 400
Plant Area
n/a
Annual Production 16,800,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $376,228 6,973,623
kWh
Natural Gas $216,874 90,121
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,072 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,370

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7111: Reduce illumination to minimum necessary levels $11,528 $700 $10,793
192,263
kWh
- $735
02 2.1233: Analyze flue gas for proper air/fuel ratio $7,435 $3,500 - $7,435
-
MMBtu
-
03 2.2447: Heat water with exhaust heat $8,382 $270 - $2,127
-
MMBtu
$6,255
04 2.2414: Use waste heat from hot flue gases to preheat $5,156 $3,125 - $5,156
-
MMBtu
-
05 2.2136: Install / repair insulation on steam lines $2,553 $2,183 - $2,553
-
MMBtu
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $70 - $70
1,172
kWh
- -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,948 $8,560 $5,948
146,835
kWh
- -
TOTAL RECOMMENDED $41,072 $18,338 $16,811
340,270
kWh
$17,271
-
MMBtu
$6,990
TOTAL IMPLEMENTED $18,370 $5,953 - $12,115
-
MMBtu
$6,255
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs