Assessment Year | 1992 |
---|---|
Principal Product | PACKAGED JUICE PRODUCTS |
NAICS |
n/a
|
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $10 M to 50M |
# of Employees | 400 |
Plant Area |
n/a
|
Annual Production | 16,800,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $376,228 | 6,973,623 |
kWh
|
$0.054 |
Natural Gas | $216,874 | 90,121 |
MMBtu
|
$2.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,072 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,370 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $11,528 | $700 |
$10,793
192,263
kWh
|
- | $735 | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $7,435 | $3,500 | - |
$7,435
-
MMBtu
|
- | |
03 | 2.2447: Heat water with exhaust heat | $8,382 | $270 | - |
$2,127
-
MMBtu
|
$6,255 | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $5,156 | $3,125 | - |
$5,156
-
MMBtu
|
- | |
05 | 2.2136: Install / repair insulation on steam lines | $2,553 | $2,183 | - |
$2,553
-
MMBtu
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $70 | - |
$70
1,172
kWh
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,948 | $8,560 |
$5,948
146,835
kWh
|
- | - | |
TOTAL RECOMMENDED | $41,072 | $18,338 |
$16,811
340,270
kWh
|
$17,271
-
MMBtu
|
$6,990 | ||
TOTAL IMPLEMENTED | $18,370 | $5,953 | - |
$12,115
-
MMBtu
|
$6,255 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs