ITAC Assessment: OK0372
ITAC logo
ITAC Assessment: OK0372
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product VARIETY OF MATERIAL ARTS
NAICS
n/a
SIC 2329: Men's and Boys' Clothing, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 2,210
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $90,500 1,405,334
kWh
Natural Gas $6,367 2,031
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,818 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,672

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2437: Recover waste heat from equipment $588 $807 - $588
-
MMBtu
02 2.7261: Install timers and/or thermostats $3,782 $2,888 - $3,782
-
MMBtu
03 2.7123: Keep lamps and reflectors clean $4,890 $16,670 $5,283
83,236
kWh
$(-393.0)
-
MMBtu
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $4,558 $9,275 $5,796
62,427
kWh
$(-1,238.0)
-
MMBtu
TOTAL RECOMMENDED $13,818 $29,640 $11,079
145,663
kWh
$2,739
-
MMBtu
TOTAL IMPLEMENTED $8,672 $19,558 $5,283
83,236
kWh
$3,389
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs