| Assessment Year | 1991 |
|---|---|
| Principal Product | INVESTMENT CASTINGS |
| NAICS |
n/a
|
| SIC | 3369: Nonferrous Foundries, Except Aluminum and Copper |
| Sales Range | $1 M to 5M |
| # of Employees | 60 |
| Plant Area |
n/a
|
| Annual Production | 252
ton
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $91,641 | 1,640,094 |
kWh
|
$0.056 |
| Natural Gas | $49,177 | 17,822 |
MMBtu
|
$2.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,787 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3511: Use plant owned transformers or lease transformers | $2,955 | $19,500 |
$2,955
-
kWh
|
- | |
| 02 | 2.2437: Recover waste heat from equipment | $2,237 | $980 | - |
$2,237
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,595 | $4,357 |
$1,595
18,757
kWh
|
- | |
| TOTAL RECOMMENDED | $6,787 | $24,837 |
$4,550
18,757
kWh
|
$2,237
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs