| Assessment Year | 1991 |
|---|---|
| Principal Product | GLASS CONTAINERS |
| NAICS |
n/a
|
| SIC | 3221: Glass Containers |
| Sales Range | $10 M to 50M |
| # of Employees | 360 |
| Plant Area |
n/a
|
| Annual Production | 96,000
ton
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $676,653 | 38,813,893 |
kWh
|
$0.017 |
| Natural Gas | $1,575,423 | 921,577 |
MMBtu
|
$1.71 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $276,953 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,555 | - |
$1,654
54,220
kWh
|
- | $(-99.0) | |
| 02 | 2.4133: Use most efficient type of electric motors | $1,330 | $1,330 |
$1,330
59,203
kWh
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $68,612 | $56,631 |
$68,612
3,060,375
kWh
|
- | - | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $50,672 | - |
$106,056
4,730,363
kWh
|
$(-55,384.0)
-
MMBtu
|
- | |
| 05 | 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust | $153,237 | - |
$301,935
9,898,886
kWh
|
$(-128,358.0)
-
MMBtu
|
$(-20,340.0) | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,547 | - |
$1,547
50,703
kWh
|
- | - | |
| TOTAL RECOMMENDED | $276,953 | $57,961 |
$481,134
17,853,750
kWh
|
$(-183,742.0)
-
MMBtu
|
$(-20,439.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs