ITAC Assessment: OK0328
ITAC logo
ITAC Assessment: OK0328
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product ENGINE OIL AND AIR PUMPS
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 270
Plant Area
n/a
Annual Production 5,700,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $725,489 15,691,091
kWh
Natural Gas $105,073 33,161
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,189 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,730

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $38,923 $18,700 $49,236
699,004
kWh
$(-10,313.0)
-
MMBtu
-
02 2.7261: Install timers and/or thermostats $1,170 $1,500 - $1,170
-
MMBtu
-
03 2.2511: Insulate bare equipment $536 $2,080 - $536
-
MMBtu
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $519 - $519
10,551
kWh
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $41 - $341
16,120
kWh
- $(-300.0)
TOTAL RECOMMENDED $41,189 $22,280 $50,096
725,675
kWh
$(-8,607.0)
-
MMBtu
$(-300.0)
TOTAL IMPLEMENTED $1,730 $1,500 $860
26,671
kWh
$1,170
-
MMBtu
$(-300.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs