ITAC Assessment: OK0325
ITAC logo
ITAC Assessment: OK0325
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product TUBE LIGHTING
NAICS
n/a
SIC 3641: Electric Lamp Bulbs and Tubes
Sales Range $1
M
to 5
M
# of Employees 75
Plant Area
n/a
Annual Production 5,200,000
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,591 1,005,862
kWh
Natural Gas $7,776 1,711
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,265 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,280

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,545 - $1,545
23,447
kWh
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $570 - $600
16,999
kWh
- $(-30.0)
03 2.7142: Utilize higher efficiency lamps and/or ballasts $652 $3,027 $588
8,792
kWh
- $64
04 2.2437: Recover waste heat from equipment $333 $1,280 - $333
-
MMBtu
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $165 - $165
2,931
kWh
- -
TOTAL RECOMMENDED $3,265 $4,307 $2,898
52,169
kWh
$333
-
MMBtu
$34
TOTAL IMPLEMENTED $2,280 - $2,310
43,377
kWh
- $(-30.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs