Assessment Year | 1990 |
---|---|
Principal Product | READY MIX CONCRETE SAND |
NAICS |
n/a
|
SIC | 3273: Ready-Mixed Concrete |
Sales Range | $1 M to 5M |
# of Employees | 12 |
Plant Area |
n/a
|
Annual Production | 351,000
ton
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $133,378 | 2,009,086 |
kWh
|
$0.066 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,808 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,283 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $6,113 | - |
$6,113
-
kWh
|
|
02 | 2.3511: Use plant owned transformers or lease transformers | $324 | - |
$324
5,569
kWh
|
|
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,971 | $4,800 |
$1,971
33,411
kWh
|
|
04 | 2.3212: Optimize plant power factor | $2,799 | $10,000 |
$2,799
47,479
kWh
|
|
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,755 | $32,000 |
$11,755
199,297
kWh
|
|
06 | 2.7261: Install timers and/or thermostats | $846 | $1,050 |
$846
14,361
kWh
|
|
TOTAL RECOMMENDED | $23,808 | $47,850 |
$23,808
300,117
kWh
|
||
TOTAL IMPLEMENTED | $7,283 | $1,050 |
$7,283
19,930
kWh
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs