Assessment Year | 1990 |
---|---|
Principal Product | WOOD & SHEET METAL PDTS. |
NAICS |
n/a
|
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
n/a
|
Annual Production | 1,560
pieces
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $61,334 | 968,933 |
kWh
|
$0.063 |
Natural Gas | $12,879 | 3,909 |
MMBtu
|
$3.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $3,416 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,211 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $578 | $437 |
$578
9,086
kWh
|
- | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $1,246 | $400 |
$1,164
18,464
kWh
|
$82 | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,387 | - |
$1,487
42,204
kWh
|
$(-100.0) | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $205 | $193 |
$205
3,224
kWh
|
- | |
TOTAL RECOMMENDED | $3,416 | $1,030 |
$3,434
72,978
kWh
|
$(-18.0) | ||
TOTAL IMPLEMENTED | $3,211 | $837 |
$3,229
69,754
kWh
|
$(-18.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs