ITAC Assessment: OK0269
ITAC logo
ITAC Assessment: OK0269
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product LIVESTOCK FEED
NAICS
n/a
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $10
M
to 50
M
# of Employees 35
Plant Area
n/a
Annual Production 60,000
ton
Production Hrs. Annual 4,165
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $61,372 1,133,060
kWh
Natural Gas $28,817 6,320
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,047 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,657

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $92 $88 $92
1,465
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $44 $103 $44
879
kWh
-
03 2.4133: Use most efficient type of electric motors $690 $1,414 $690
11,723
kWh
-
04 2.4312: Improve lubrication practices $1,262 - $1,262
21,395
kWh
-
05 2.1222: Install turbulators $700 $760 - $700
-
MMBtu
06 2.2113: Repair or replace steam traps $1,259 $300 - $1,259
-
MMBtu
TOTAL RECOMMENDED $4,047 $2,665 $2,088
35,462
kWh
$1,959
-
MMBtu
TOTAL IMPLEMENTED $2,657 $491 $1,398
23,739
kWh
$1,259
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs