| Assessment Year | 1988 |
|---|---|
| Principal Product | SAFETY HARDWARE, FORGING |
| NAICS |
n/a
|
| SIC | 3429: Hardware, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 100 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $122,899 | 2,053,927 |
kWh
|
$0.060 |
| Natural Gas | $105,063 | 35,725 |
MMBtu
|
$2.94 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,394 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,411 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $320 | $213 |
$320
6,155
kWh
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $409 | - |
$509
20,223
kWh
|
- | $(-100.0) | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $682 | - |
$682
27,257
kWh
|
- | - | |
| 04 | 2.3212: Optimize plant power factor | $2,706 | $7,500 |
$2,706
-
kWh
|
- | - | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $12,277 | $22,000 | - |
$12,277
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $16,394 | $29,713 |
$4,217
53,635
kWh
|
$12,277
-
MMBtu
|
$(-100.0) | ||
| TOTAL IMPLEMENTED | $1,411 | $213 |
$1,511
53,635
kWh
|
- | $(-100.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs