ITAC Assessment: OK0254
ITAC logo
ITAC Assessment: OK0254
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product DISP. REFRIG. CYLINDERS
NAICS
n/a
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area
n/a
Annual Production 2,000,000
pieces
Production Hrs. Annual 5,376
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $170,650 3,818,288
kWh
Natural Gas $48,286 15,480
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,988 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,717

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $4,084 - $4,084
88,511
kWh
- -
02 2.7111: Reduce illumination to minimum necessary levels $11,072 $925 $11,072
199,883
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $118 $78 $118
1,758
kWh
- -
04 2.7221: Lower temperature during the winter season and vice-versa $187 $513 - $187
-
MMBtu
-
05 2.4133: Use most efficient type of electric motors $400 $380 $400
8,792
kWh
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $127 - $167
6,741
kWh
- $(-40.0)
TOTAL RECOMMENDED $15,988 $1,896 $15,841
305,685
kWh
$187
-
MMBtu
$(-40.0)
TOTAL IMPLEMENTED $11,717 $1,383 $11,757
217,174
kWh
- $(-40.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs