Assessment Year | 1988 |
---|---|
Principal Product | ELECTRIC SWITCHGEARS |
NAICS |
n/a
|
SIC | 3613: Switchgear and Switchboard Apparatus |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
n/a
|
Annual Production | 1,100
pieces
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $142,068 | 2,443,142 |
kWh
|
$0.058 |
Natural Gas | $56,726 | 17,675 |
MMBtu
|
$3.21 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $35,338 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $604 | - |
$724
23,447
kWh
|
- | $(-120.0) | |
02 | 2.2437: Recover waste heat from equipment | $3,473 | $525 | - |
$3,473
-
MMBtu
|
- | |
04 | 2.4239: Eliminate or reduce compressed air usage | $13,831 | $275 |
$13,831
446,073
kWh
|
- | - | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $5,927 | $1,500 | - |
$5,927
-
MMBtu
|
- | |
06 | 2.8114: Change rate schedules or other changes in utility service | $7,063 | $8,400 |
$7,063
-
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $822 | $740 |
$822
14,654
kWh
|
- | - | |
08 | 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown | $3,618 | $1,200 |
$341
11,137
kWh
|
$3,277
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $35,338 | $12,640 |
$22,781
495,311
kWh
|
$12,677
-
MMBtu
|
$(-120.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs