Assessment Year | 1988 |
---|---|
Principal Product | STEEL FABRICATION |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 55 |
Plant Area |
n/a
|
Annual Production | 35
pieces
|
Production Hrs. Annual | 4,300
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $60,923 | 808,910 |
kWh
|
$0.075 |
Natural Gas | $6,899 | 1,581 |
MMBtu
|
$4.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,468 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,478 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,990 | $1,597 |
$2,185
33,705
kWh
|
- | $(-195.0) | |
02 | 2.7261: Install timers and/or thermostats | $1,224 | $1,710 | - |
$1,224
-
MMBtu
|
- | |
03 | 2.2437: Recover waste heat from equipment | $1,523 | $645 | - |
$1,523
-
MMBtu
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $651 | - |
$741
11,430
kWh
|
- | $(-90.0) | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $80 | $64 |
$80
1,172
kWh
|
- | - | |
TOTAL RECOMMENDED | $5,468 | $4,016 |
$3,006
46,307
kWh
|
$2,747
-
MMBtu
|
$(-285.0) | ||
TOTAL IMPLEMENTED | $3,478 | $2,419 |
$821
12,602
kWh
|
$2,747
-
MMBtu
|
$(-90.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs