ITAC Assessment: OK0245
ITAC logo
ITAC Assessment: OK0245
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product STEEL FABRICATION
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area
n/a
Annual Production 35
pieces
Production Hrs. Annual 4,300
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,923 808,910
kWh
Natural Gas $6,899 1,581
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,468 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,478

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,990 $1,597 $2,185
33,705
kWh
- $(-195.0)
02 2.7261: Install timers and/or thermostats $1,224 $1,710 - $1,224
-
MMBtu
-
03 2.2437: Recover waste heat from equipment $1,523 $645 - $1,523
-
MMBtu
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $651 - $741
11,430
kWh
- $(-90.0)
05 2.7142: Utilize higher efficiency lamps and/or ballasts $80 $64 $80
1,172
kWh
- -
TOTAL RECOMMENDED $5,468 $4,016 $3,006
46,307
kWh
$2,747
-
MMBtu
$(-285.0)
TOTAL IMPLEMENTED $3,478 $2,419 $821
12,602
kWh
$2,747
-
MMBtu
$(-90.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs