ITAC Assessment: OK0229
ITAC logo
ITAC Assessment: OK0229
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product INJECTION MOLDINGS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 4,500
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $151,395 2,596,424
kWh
Natural Gas $20,908 4,963
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,875 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,491

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $114 - $154
4,396
kWh
- $(-40.0)
02 2.2414: Use waste heat from hot flue gases to preheat $577 - - $577
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $433 - $433
6,155
kWh
- -
04 2.4133: Use most efficient type of electric motors $1,236 $1,031 $1,236
23,740
kWh
- -
05 2.3212: Optimize plant power factor $3,708 $2,200 $3,708
-
kWh
- -
06 2.4322: Use or replace with energy efficient substitutes $3,856 $1,100 $3,856
109,320
kWh
- -
07 2.7111: Reduce illumination to minimum necessary levels $4,951 $3,660 $4,951
80,891
kWh
- -
TOTAL RECOMMENDED $14,875 $7,991 $14,338
224,502
kWh
$577
-
MMBtu
$(-40.0)
TOTAL IMPLEMENTED $5,491 $3,231 $5,531
34,291
kWh
- $(-40.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs