ITAC Assessment: OK0199
ITAC logo
ITAC Assessment: OK0199
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product GALVANIZED POLES
NAICS
n/a
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area
n/a
Annual Production 2,550
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $92,124 1,786,049
kWh
Natural Gas $135,140 37,219
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $88,595 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,817

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7111: Reduce illumination to minimum necessary levels $3,090 $160 $3,090
44,842
kWh
- -
02 2.2511: Insulate bare equipment $19,130 $14,112 - $19,130
-
MMBtu
-
03 2.2514: Cover open tanks $63,648 $7,814 - $63,648
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,727 $5,271 $3,182
46,307
kWh
- $(-455.0)
TOTAL RECOMMENDED $88,595 $27,357 $6,272
91,149
kWh
$82,778
-
MMBtu
$(-455.0)
TOTAL IMPLEMENTED $5,817 $5,431 $6,272
91,149
kWh
- $(-455.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs