ITAC Assessment: OK0195
ITAC logo
ITAC Assessment: OK0195
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product PUMPS & MOTORS
NAICS
n/a
SIC 3561: Pumps and Pumping Equipment
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area
n/a
Annual Production 1,500
pieces
Production Hrs. Annual 5,100
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $353,724 6,514,947
kWh
Natural Gas $77,915 21,459
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,397 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,312

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7111: Reduce illumination to minimum necessary levels $1,989 $500 $1,989
43,669
kWh
- -
02 2.2532: Use only amount of air necessary to prevent explosion hazard $2,085 $214 $372
12,603
kWh
$1,713
-
MMBtu
-
03 2.2424: Use heat in flue gases to preheat products or materials $2,520 $3,000 - $2,520
-
MMBtu
-
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $12,902 - $12,902
-
kWh
- -
05 2.3191: Use demand controller or load shedder $1,289 $1,200 $1,289
-
kWh
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $582 - $682
22,860
kWh
- $(-100.0)
07 2.2223: Enhance sensitivity of temperature control and cutoff $2,030 $1,200 $2,030
41,325
kWh
- -
TOTAL RECOMMENDED $23,397 $6,114 $19,264
120,457
kWh
$4,233
-
MMBtu
$(-100.0)
TOTAL IMPLEMENTED $21,312 $5,900 $18,892
107,854
kWh
$2,520
-
MMBtu
$(-100.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs