Assessment Year | 1986 |
---|---|
Principal Product | REMANUF JET ENGINE PARTS |
NAICS |
n/a
|
SIC | 3724: Aircraft Engines and Engine Parts |
Sales Range | $10 M to 50M |
# of Employees | 370 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 5,600
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $254,560 | 5,202,228 |
kWh
|
$0.049 |
Natural Gas | $59,113 | 15,954 |
MMBtu
|
$3.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $138,061 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $118,293 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,426 | $9,484 |
$8,552
189,039
kWh
|
- | $(-126.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,006 | $1,225 |
$3,006
64,478
kWh
|
- | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $10,057 | $3,500 | - |
$10,057
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,945 | $7,768 |
$5,310
112,251
kWh
|
$(-365.0)
-
MMBtu
|
- | |
05 | 2.4322: Use or replace with energy efficient substitutes | $11,547 | $32,800 | - |
$11,547
-
MMBtu
|
- | |
06 | 3.6124: Burn waste oil for heat | $3,391 | $2,400 |
$(-230.0)
(-4,982)
kWh
|
$3,621
-
MMBtu
|
- | |
07 | 3.4115: Recover and reuse cooling water | $96,689 | $52,800 |
$844
24,033
kWh
|
- | $95,845 | |
TOTAL RECOMMENDED | $138,061 | $109,977 |
$17,482
384,819
kWh
|
$24,860
-
MMBtu
|
$95,719 | ||
TOTAL IMPLEMENTED | $118,293 | $89,100 |
$844
24,033
kWh
|
$21,604
-
MMBtu
|
$95,845 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs